Optima were recently asked to advise on a safety guarding application for one of our customers. 

There had been a number of false trips of the laser scanner causing the machine to stop. A plastic chain ‘barrier’ had been fitted as a temporary measure with instructions to operators to not breach the barrier whilst the machine was running. 

The customer naturally wanted this rectifying as soon as possible. Optima carried out a service visit to site.

On the site visit, our engineer noted that the scanner was showing a code which indicated that the front screen required cleaning.

 Once the screen was cleaned thoroughly the scanner did not show any faults or errors and was in normal run mode.

 

Further checks on the original software were made to ensure the scanner configuration met the requirements of the safety guarding application. 

The diagrams to the left show the Warning Field configuration (Yellow) and the Protective Field (Red). Both of these were confirmed to be operational. 

The warning field causes the klaxon to operate but does nto stop the machine. The protective field causes an emergency stop of the machine.

We did find some concerns that needed addressing.

1. None of the scanner safety circuit had been documented on any drawings.

2. Non-compliance with EN999 ‘Safety of machinery. This defines the positioning of protective equipment in respect of approach speeds of parts of the human body’. It includes a formula to be used to calculate the distance from a hazard that a safety zone must be triggered. 

Based on the stopping times of the machine, the scanner was placed too close to the machine to be effective in an emergency.

We are working closedly with our customer to assist them with this application and help them achieve a safe and effective solution to this.

If you need any support with safety applications or other upgrades, please get in touch.. 

First Batch of UL-Control Panels Finished and ready for shipping to the USA

Not content with supplying our UK and European customers with quality control panels from our workshop, we thought to look further afield. Far across the Atlantic Ocean in fact. Optima turned our engineering skills to designing a full process control system for a customer in the USA. Here are some of the panels we built for this project.

This is our first batch of UL-Rated control panels completed and ready for storage prior to shipping to the United States. This is part of a fully integrated Rockwell Automation control system featuring ControlLogix PLC’s with Guard Logix Safety and PowerFlex Drives.

Outsourcing industrial automation: The essential considerations

In this article, we discuss whether it is more beneficial to outsource your engineering design activities completely or whether a blend of internal and external skills can offer more of a benefit to your company.

Automated control systems are a critical component in the backbone of modern manufacturing. It is virtually impossible to imagine conceiving a manufacturing process without the help of specialized digital control systems. Their subsequent maintenance is even harder to imagine. Today’s plant managers are faced with the dilemma of either hiring in-house engineering resource or outsourcing the service completely. Often a mix of both is considered the ideal solution. Below we suggest several key issues to consider if faced with forming such a strategy.

1. How big is your manufacturing operation? – Hiring full-time in-house engineers can prove costly if they cannot be fully utilised. Often companies find that once a specific project is completed and the system is “bedded in”, the control system reliability improves reducing any ongoing maintenance needs. Outsourcing the control system design and maintenance resource offers the flexibility and on-demand service sought by smaller companies at a more economic cost.

2. Do you require specialised skills and expertise only for a specific project? – As control system technologies evolve, it is necessary to maintain a company’s in-house engineers awareness and skill levels. This must be a considered investment. Extensive training is often needed which attracts additional cost to your company. Outsourced engineers need to stay at the forefront of engineering technologies to ensure their own sustained income and spread the cost annually across multiple projects.

3. How complex is the project and what risk does it carry? – Modern, high-feature control equipment cannot be upgraded using traditional methods. To attempt to do so without the specialist knowledge required may result in higher costs and running over budgeted times. Outsourced system integrators have a wealth of experience providing better guarantees on the methods used to update equipment and thus will lower the overall risk.

4. Health & safety and risk mitigation – Only the control equipment designed to meet a company’s health and safety obligations match the complexity of today’s regulations. The ability to engineer a compliant system is a legal requirement and not to be underestimated.

5. Project time-scales – It goes without saying that control system upgrades require machine downtime to accommodate installation and commissioning activities. Automation companies have the benefit of project teams that can effectively reduce machine downtimes significantly.

6. Collaboration is key – Ideally, as mentioned above, a combination of an internal project engineer or team working closely with the outsourced project design and delivery company works better for a successful delivery and ownership of a project. Making sure both teams cooperate closely and trust each other is essential. Information flow, clarity of objectives and clear design principles are three pre-requisites that will ensure good project management and mutual understanding.

7. Does the integrator understand your business? – A steep learning curve  should be expected at the start of every project for any external engineering team whilst acquiring detailed knowledge of the application. Establishing long standing business relationships, based on performance and trust gained over numerous collaborative projects will promote a better understanding of the clients’ processes for the integrator. This understanding will bring real time and cost savings together with a level of trust that makes working together more natural.